PROJECT

The Google site, Gromstul

Google-tomta, Gromstul

Temporary site bridge for heavy construction traffic.

The project

In connection with the civil engineering works on the Google site at Gromstul in Skien, a temporary bridge solution was needed to ensure passage and efficient logistics for the construction traffic.

Frico Group supplied the solution on behalf of Marthinsen & Duvholt.

Frico Group’s delivery

Frico Group supplied a temporary site bridge with a span of approx. 24.75 metres and a clear internal width of approx. 4.5 metres.

The bridge was designed for a 10-tonne axle load and a gross weight of 60 tonnes, and was intended for construction traffic. The bridge solution was delivered with a deck of timber mats.

The modular solution provided a robust temporary connection adapted to heavy transport and logistics on the site.

Efficient access during the construction period

On large construction sites, good transport routes are essential for safe, efficient execution. The temporary site bridge helped establish the necessary connection for heavy construction traffic throughout the project period.

The project shows how Frico Group’s modular site bridges can be adapted to the project’s requirements for span, width and load capacity.

Project facts

  • Customer: Marthinsen & Duvholt
  • Project: The Google site, Gromstul
  • Location: Gromstul, Skien
  • Solution: Temporary site bridge
  • Span: approx. 24.75 metres
  • Clear width: approx. 4.5 metres
  • Capacity: 10-tonne axle load / 60-tonne gross weight
  • Year: 2023/2024

About the project

LOCATION
PERIOD
SERVICES

Photos from the project

More projects

E18 Langangen–Rugtvedt – midlertidig gangbru

E18 Langangen–Rugtvedt – temporary footbridge

Slottsfjellfestivalen

Slottsfjellfestivalen

Tons of Rock

Tons of Rock