The Varberg Tunnel is a major and technically advanced infrastructure project in which the contractor Implenia is building a railway tunnel and four bridges in Varberg in 2020–2024.
The project improves the transport network in Varberg and increases safety and capacity for both rail and road traffic. The tunnel has four portals.
100,000 cubic metres of falsework
Frico Group supplies falsework for the tunnel portals and the bridges, around 100,000 cubic metres in total over the course of the project. The falsework is designed for heavy concrete loads and adapted to each pour, so the work can follow the programme.
The Varberg Tunnel shows Frico Group’s ability to deliver large volumes of falsework over a long period to technically demanding infrastructure projects.
Project facts
- Project: Varberg Tunnel
- Contractor: Implenia
- Hire period: 2020–2024
- Tunnel portals: 4
- Bridges: 4
- Falsework volume: approx. 100,000 m³
- Sector: Infrastructure