Temporary site bridge for construction site logistics.

The project

In connection with the construction works at Gjerdrums vei 10 in Nydalen, a temporary bridge solution was needed to ensure access and efficient construction traffic on site.

Frico Group supplied the site bridge on behalf of Vedal Entreprenør.

Frico Group’s delivery

Frico Group supplied a temporary site bridge with a span of approx. 29 metres and an internal width of approx. 3.6 metres.

The bridge was designed for a 10-tonne axle load and a gross weight of 65 tonnes, and was intended for construction traffic.

The delivery consisted of load-bearing truss girders and steel beams as bearings for the bridge deck. The modular solution provided a robust temporary connection adapted to transport and logistics throughout the construction period.

Access for heavy construction traffic

Good site logistics were important in the project, and the temporary site bridge made it possible to establish an efficient connection for heavy vehicles.

The project shows how Frico Group’s modular site bridges can be used to establish temporary access on construction sites where terrain or existing conditions make ordinary passage difficult.

Project facts

  • Customer: Vedal Entreprenør
  • Project: Gjerdrums vei 10 / Nydalen
  • Location: Nydalen, Oslo
  • Solution: Temporary site bridge
  • Span: approx. 29 metres
  • Internal width: approx. 3.6 metres
  • Capacity: 10-tonne axle load / 65-tonne gross weight
  • Year: 2023

About the project

LOCATION
PERIOD
SERVICES

Photos from the project

More projects

Dødsing i Tønsberg

Death diving in Tønsberg

Alpine World Cup City Event – Holmenkollen

Alpine World Cup City Event – Holmenkollen

Foynhagen, Tønsberg

Foynhagen, Tønsberg